1. As explained within the Chapter 8, intangible asset, Australian accounting standards now prohibit goodwill from being subject to amortisation. Rather, there is a requirement that goodwill be subject to impairment testing. In relation to impairment testing of goodwill, Petersen and Plenborg (2010, p.420) state:

Many argue that an impairment test only approach seems a logical step in the development of accounting for goodwill. First, the underlying logic for removing the traditional amortization methodology is that the amortization on a straight-line basis over a number of years contains no information value for those using financial statements (Jennings et al., 2001). Moreover, IFRS 3 (IASB, 2004b) no longer requires that companies perform the almost impossible task of estimating the useful life of goodwill (Jansson et al. 2004). Second, the impairment approach should provide users of financial statements with better information, as goodwill is not automatically amortized (Colquitt and Wilson, 2002; Bens and Heltzer, 2005). Finally, goodwill impairment tests would be operational and capture a decline in the value of goodwill (Donnelly and Keys, 2002).

REQUIRED

You are to provide a clear argument as to why you agree or disagree with the perspectives provided in the paragraph above.

2. On 1 July 2015 Kruger Ltd privately issues $1 million in six-year debentures, which pay interest each six months at a coupon rate of 6 per cent per annum. At the time of issuing the securities, the market requires a rate of return of 4 per centConsistent with the requirements of AASB 9, the debentures are accounted for using the effective interest method.

REQUIRED
(a) Determine the fair value of the debentures at the time of issue (which will also be their issue price).
(b) Provide the journal entries at:
(i) 1 July 2015
(ii) 31 December 2015
(iii) 30 June 2016.

3. Sun City Limited commences construction of a multi-purpose water park on 1 July 2014 for Pretoria Limited. Sun City Limited signs a fixed-price contract for total revenues of $50 million. The project is expected to be completed by the end of 2017 and Pretoria Limited controls the asset throughout the period of construction. The expected cost as at the commencement of construction is $38 million. The estimated costs of a construction project might change throughout the project—in this example, they do change. The following data relates to the project (the financial years end on 30 June):

Search Here

Latest Reviews

  • Marcus
    30 Apr, 2019

    My assignment help services are provided in the best way by this website. The writers have completed my assignment in such a way that they helped me increase my overall performance.

  • Emy
    29 Apr, 2019

    Awesome work done by the experts of this company. I visited this site to get math assignment completed. My assignment was complete in every aspect. Thanks to the professionals who provided assignment writing help.

  • Darina
    25 Apr, 2019

    All thanks to the writers of Assignment Help 4 Me who completed my Physics assignment in the right manner. The structure of the assignment was totally customized according to my needs and that too at cheap prices.

View All Reviews

Facebook

Assignment Help 4 Me